[brusselsairport.be] Renovation of runway 25R/07L at Brussels Airport in 2020

Forwarded from De : Press office
Date: lun. 9 sept. 2019 à 14:21
Subject: Renovation of runway 25R/07L at Brussels Airport in 2020
To:



brussels airport_baseline_Q.tif


91D68EC


Brussels Airport, 9 September 2019


Renovation of runway 25R/07L at Brussels Airport in 2020
After the thorough renovation of runways 25L/07R in 2015 and 01/19 in 2016, Brussels Airport Company will be renovating runway 25R/07L from 13 July to 23 August 2020.
24 years after the previous renovation works on this runway, in 1996, the entire runway needs to be closed for renovation to guarantee the safe landing and take-off of aircraft.

Due to the closure of this runway, runway use during the maintenance work at Brussels Airport is different from that under normal circumstances. To limit the duration of the runway closure and the impact of the renovation works, work is carried out 24 hours a day, 7 days a week.


Press Office: Brussels Airport Company – Corporate Communications – Tel. + 32 2 753 53 53